Marram · Company OKRs · Q1 2027
Our mid-quarter check-in, as of Monday, February 15. Four objectives, eleven key results. Nine are on track or ahead, one is at risk, and one is behind. The one that's behind is payroll export, and we've changed our forecast for it below.
average progress across all eleven
of the quarter gone: 6 of 13 weeks
Each bar runs from where we started to the target. The notch marks 46%, where a steady pace would be today. Ahead is 20 points or more past the notch. On track is no more than 10 short of it. At risk is 11 to 25 short. Behind is more than 25 short.
Ngozi Eze, Product
Why 1.3 is at risk. The new setup checklist cut the tickets about importing staff lists. Tickets about shift templates haven't moved. A library of ready-made templates ships on Wednesday, February 24, and we'll know by mid-March whether it worked.
Tomasz Wrona, Sales
Why 2.2 is behind. The export for the two payroll providers most agencies use shipped on February 8, three weeks late. Six agencies added it in its first week.
What we're doing. Sales is calling the 51 agencies that asked for it by name. One engineer has moved from reports to the export until Friday, March 12.
What we now expect. About 62 by March 31, not 80. We'd rather say that in February than explain it in April.
Leilani Kahale, Engineering
Bram de Wit, People
We score the quarter together on Thursday, April 1. Until then, if a number here looks wrong to you, tell the name next to it. From Hana Sørensen and the leadership team.